PRINCE2 PRINCE2-Practitioner Exam Questions


Vendor Name: PRINCE2
Certification Name:PRINCE2 Certification
Exam Name:PRINCE2 Practitioner Exam

  • 90 Days Free PRINCE2-Practitioner Updates
  • Experts Verified Answers
  • Printable PDF File Format
  • Exam Passing Assurance

Get 100% Real PRINCE2-Practitioner Exam Questions With Verified Answers As Seen in the Real Exam. PRINCE2 Practitioner Exam Dumps are Updated Frequently and Reviewed by Industry TOP Experts for Passing PRINCE2 Certification Exam Quickly and Hassle Free.

Total Questions Answers: 282
Last Updated: 8-Sep-2023
Available with 3, 6 and 12 Months Free Updates Plans
PDF File: $31.99

Test Engine: $37.99

PDF + Online Test: $49.99

PRINCE2 PRINCE2-Practitioner Exam Questions


If you are not prepared for PRINCE2 Certification PRINCE2-Practitioner exam questions and want to get some help so, now you do not need to take tension. You can pass PRINCE2 Certification exam very simply and easily with our PRINCE2 Practitioner Exam dumps questions answers. 

The PRINCE2 Certification exam questions PDF and test engine having most updated and verified PRINCE2 PRINCE2-Practitioner questions answers cover all the exam topics and course outline completely. Online PRINCE2 Certification dumps help you to get prepare and familiar with the real exam situation. 

PRINCE2 PRINCE2-Practitioner dumps questions answers are high-quality and accurate prepared with a view to provide you maximum ease and complete confidence in your preparation PRINCE2 Certification practice questions are so comprehensive that you need not to run after any other source and are presented in both PRINCE2 Pdf files and online practice test formats to be read easily on mobile device and laptop. In spite of trying unauthentic and sub standard PRINCE2 practice exams material make right choice at right time.

Our PRINCE2 PRINCE2-Practitioner exam dumps study material would prove to be the best choice to pass your PRINCE2 Certification PRINCE2-Practitioner exam in first try. Dumps4free is providing up-to-date PRINCE2 Practitioner Exam pdf files. 



PRINCE2 Practitioner Exam Exams
  • PRINCE2 Prince2-Foundation Dumps
  • PRINCE2 PRINCE2-Agile-Foundation Dumps
  • Assurance

    PRINCE2 PRINCE2-Practitioner dumps are updated according to latest PRINCE2 Practitioner Exam exam questions.

  • Demo

    Free PRINCE2 Certification PRINCE2-Practitioner dumps questions answers demo available before purchase. Contact out Live chat person

  • Validity

    PRINCE2 PRINCE2-Practitioner Dumps pdf is valid and tested by experts with their right answers.

  • Success

    Your success is assured with PRINCE2 Practitioner Exam PRINCE2-Practitioner exam dumps!

PRINCE2-Practitioner Exam Sample Questions:



As a result of experiences on previous projects, a change authority has been established for the Health and
Safety Training Project. A key client for the training materials has a representative on the project board. Should their interests be represented within the change authority for the project, and why?

 

Yes, because this will give them a better understanding of the training materials.

 

Yes, because a change authority should consider external stakeholder needs.

 

No, because the change authority should be internal to the ABC organization.

 

No, because their project board member will be able to agree any required changes.


No, because their project board member will be able to agree any required changes.






During previous projects, stakeholders became confused when using a number of separate project registers.
Therefore, when preparing the risk management approach, the project manager created a risk register template
and added it to an integrated project register. This register is a spreadsheet that includes project assumptions,
issues, dependencies, and now risks, on separate pages.
Is this appropriate for a risk register, and why?

 

Yes, because the project registers should be tailored to meet the needs of the organization.

 

Yes, because risks are often identified as a result of issues being raised.

 

No, because an integrated project register should include the quality register as well.

 

No, because assumptions and dependencies are sources of risk.


No, because an integrated project register should include the quality register as well.






The Sales Director would like to add a new company logo to the 'marketing material'. The change to the
project scope has been approved by the project board. It is expected to delay product and stage completion
date by 3 days and cost £900. The stage 2 cost tolerance of +£1,000 has not been used. The change budget of
£500 has not been used.
Which option describes how this change should be funded?

 

£400 of the stage 2 cost tolerance and the £500 change budget should be used.

 

£900 needed for the change should be taken from the stage 2 cost tolerance.

 

£900 of additional funding will need to be requested to pay for the change.

 

£400 will need to be requested in addition to the £500 change budget.


£400 will need to be requested in addition to the £500 change budget.






The project board has asked user and supplier assurance to review all product descriptions relating to the updated corporate quality procedures', prior to authorizing the stage plan for stage 3. Is this appropriate as part of the 'directing a project' process, and why?

 

Yes, because project assurance should assess whether all stakeholders have been identified, if requested by the project board.

 

Yes, because project assurance should review the stage 3 plan for viability, if requested by the project
board.

 

No, because the project manager is responsible for writing product descriptions when creating the stage 3 plan.

 

No, because the project board should review new product descriptions before they authorize the stage 3 plan.


No, because the project board should review new product descriptions before they authorize the stage 3 plan.






The project is in stage 3. Zero time tolerance has been given for this stage. When checking progress, the project manager noticed that the checkpoint report from the external supplier of the 'e-learning course' is late. As work package progress information is missing, the project manager has decided to raise an exception report. Is this an appropriate action, and why?

 

Yes, because an exception report should be used to request guidance on how this situation should be
handled.

 

Yes, because there is zero time tolerance for this stage the checkpoint report must be delivered on time.

 

No, because the project manager should check the operations and maintenance interfaces in the work
package first.

 

No, because the team plan should be discussed with the supplier to check whether work will be
completed on time.


Yes, because an exception report should be used to request guidance on how this situation should be
handled.