Home / PRINCE2 / PRINCE2 Certification / PRINCE2-Practitioner - PRINCE2 Practitioner Exam

Latest PRINCE2-Practitioner Exam Questions


Question # 1



As a result of experiences on previous projects, a change authority has been established for the Health and
Safety Training Project. A key client for the training materials has a representative on the project board. Should their interests be represented within the change authority for the project, and why?

A.

Yes, because this will give them a better understanding of the training materials.

B.

Yes, because a change authority should consider external stakeholder needs.

C.

No, because the change authority should be internal to the ABC organization.

D.

No, because their project board member will be able to agree any required changes.




D.
  

No, because their project board member will be able to agree any required changes.







Question # 2



During previous projects, stakeholders became confused when using a number of separate project registers.
Therefore, when preparing the risk management approach, the project manager created a risk register template
and added it to an integrated project register. This register is a spreadsheet that includes project assumptions,
issues, dependencies, and now risks, on separate pages.
Is this appropriate for a risk register, and why?

A.

Yes, because the project registers should be tailored to meet the needs of the organization.

B.

Yes, because risks are often identified as a result of issues being raised.

C.

No, because an integrated project register should include the quality register as well.

D.

No, because assumptions and dependencies are sources of risk.




C.
  

No, because an integrated project register should include the quality register as well.







Question # 3



The Sales Director would like to add a new company logo to the 'marketing material'. The change to the
project scope has been approved by the project board. It is expected to delay product and stage completion
date by 3 days and cost £900. The stage 2 cost tolerance of +£1,000 has not been used. The change budget of
£500 has not been used.
Which option describes how this change should be funded?

A.

£400 of the stage 2 cost tolerance and the £500 change budget should be used.

B.

£900 needed for the change should be taken from the stage 2 cost tolerance.

C.

£900 of additional funding will need to be requested to pay for the change.

D.

£400 will need to be requested in addition to the £500 change budget.




D.
  

£400 will need to be requested in addition to the £500 change budget.







Question # 4



The project board has asked user and supplier assurance to review all product descriptions relating to the updated corporate quality procedures', prior to authorizing the stage plan for stage 3. Is this appropriate as part of the 'directing a project' process, and why?

A.

Yes, because project assurance should assess whether all stakeholders have been identified, if requested by the project board.

B.

Yes, because project assurance should review the stage 3 plan for viability, if requested by the project
board.

C.

No, because the project manager is responsible for writing product descriptions when creating the stage 3 plan.

D.

No, because the project board should review new product descriptions before they authorize the stage 3 plan.




D.
  

No, because the project board should review new product descriptions before they authorize the stage 3 plan.







Question # 5



The project is in stage 3. Zero time tolerance has been given for this stage. When checking progress, the project manager noticed that the checkpoint report from the external supplier of the 'e-learning course' is late. As work package progress information is missing, the project manager has decided to raise an exception report. Is this an appropriate action, and why?

A.

Yes, because an exception report should be used to request guidance on how this situation should be
handled.

B.

Yes, because there is zero time tolerance for this stage the checkpoint report must be delivered on time.

C.

No, because the project manager should check the operations and maintenance interfaces in the work
package first.

D.

No, because the team plan should be discussed with the supplier to check whether work will be
completed on time.




A.
  

Yes, because an exception report should be used to request guidance on how this situation should be
handled.







Question # 6



The 'capability to provide health and safety training' has been delivered. During the 'closing a project' process,
the marketing department sent an e-mail to all key customers reminding them of the deadline to comply with
the new government legislation, with an aim to build relationships with their customers.
Which theme is being applied?

A.

Risk.

B.

Organization.

C.

Plans.

D.

Change.




B.
  

Organization.







Question # 7



The executive has asked the project manager to plan for the 'e-learning course' to be used as soon as it is accredited. The aim is to start selling the 'e-learning course' while the remainder of the outputs relating to classroom-based delivery are finished. The sales of the 'e-learning course' will be entered into the business case. Why is the executive's decision to deliver the benefits early appropriate for managing the business case?

 

A.

Because organizations with mature project management often include the early justification for the
project in the business case.

B.

Because the outputs being delivered incrementally will be beneficial and will allow the business case to be justified.

C.

Because one of the PRINCE2 principles is that a project should focus on products to deliver the outputs early.

D.

Because the business case should be updated after every increment of the 'e-learning course'.




C.
  

Because one of the PRINCE2 principles is that a project should focus on products to deliver the outputs early.







Question # 8



The Health and Safety Training Project is part of a strategic program for ABC. The updated benefits
management approach needs to be checked when the products are being handed over. This check should
ensure that it includes appropriate activities to assess whether the actual course sales meet the agreed forecast
in the business case.
Which role should undertake this review as part of the 'closing a project' process?

A.

Program management.

B.

Project board.

C.

Project manager.

D.

Project assurance.




C.
  

Project manager.







Question # 9



The project is using PRINCE2's recommended risk management procedure. In the 'identify' step, a risk was
recorded in the risk register: ''If the 'accredited classroom-based course' is delayed, there is a threat that work
on the 'e-learning course' will be delayed, resulting in the 'accredited e-learning course' not being ready for the
'pilot courses'.''
In the 'implement' step, a risk response was decided: ''Work will start incrementally on the 'e-learning course'
whenever a part of the 'classroom-based training materials' gains accreditation''.
Is this appropriate, and why?

A.

Yes, because delivering incrementally will reduce the impact of the threat.

B.

Yes, because a risk response needs to be implemented for this major threat.

C.

No, because risks responses should be identified as part of the 'plan' step.

D.

No, because a risk action should be allocated to implement a response




B.
  

Yes, because a risk response needs to be implemented for this major threat.







Question # 10



The project is approaching the end of stage 3 and the pilot courses have been planned. The project manager is now undertaking the 'managing a stage boundary' process.
Which action should the project manager undertake as part of the 'update the business case' activity?

A.

Identify the dependencies between the activities required to run the 'delivered pilot courses' during stage 4.

B.

Revise the overall plan and resources to complete the project, based on actuals from the stage 3 plan.

C.

Review the performance of the external suppliers who worked on delivery of the 'e-learning course'
during stage 3.

D.

Re-plan when the number of learners using the pilot course, and their increased knowledge, will be
measured during stage 4.




A.
  

Identify the dependencies between the activities required to run the 'delivered pilot courses' during stage 4.






Get 282 PRINCE2 Practitioner Exam questions Access in less then $0.12 per day.

Total Questions Answers: 282
Last Updated: 29-Oct-2024
Available with 1, 3, 6 and 12 Months Free Updates Plans
PDF: $15 $64

Test Engine: $20 $80

PDF + Engine: $25 $99


PRINCE2 PRINCE2-Practitioner Dumps - Real Exam Questions


Exam Code: PRINCE2-Practitioner
Exam Name: PRINCE2 Practitioner Exam

  • 90 Days Free Updates
  • PRINCE2 Experts Verified Answers
  • Printable PDF File Format
  • PRINCE2-Practitioner Exam Passing Assurance

Get 100% Real PRINCE2-Practitioner Exam Dumps With Verified Answers As Seen in the Real Exam. PRINCE2 Practitioner Exam Exam Questions are Updated Frequently and Reviewed by Industry TOP Experts for Passing PRINCE2 Certification Exam Quickly and Hassle Free.

PRINCE2 PRINCE2-Practitioner Dumps


Struggling with PRINCE2 Practitioner Exam prep? Get the edge you need!

Our carefully created PRINCE2-Practitioner dumps give you the confidence to pass the exam. We offer:

  • Up-to-date PRINCE2 Certification practice questions: Stay current with the latest exam content.
  • PDF and test engine formats: Choose the study tools that work best for you.
  • Realistic PRINCE2 PRINCE2-Practitioner practice exam: Simulate the real exam experience and boost your readiness.
Pass your PRINCE2 Certification exam with ease. Try our study materials today!


Ace your PRINCE2 Certification exam with confidence!

We provide top-quality PRINCE2-Practitioner exam dumps materials that are:
  • Accurate and up-to-date: Reflect the latest PRINCE2 exam changes and ensure you are studying the right content. 
  • Comprehensive: Cover all exam topics so you do not need to rely on multiple sources. 
  • Convenient formats: Choose between PDF files and online PRINCE2 Practitioner Exam practice test for easy studying on any device.
Do not waste time on unreliable PRINCE2-Practitioner practice test. Choose our proven PRINCE2 Certification study materials and pass with flying colors.

Try Dumps4free PRINCE2 Practitioner Exam 2024 PDFs today!

  • Assurance

    PRINCE2 Practitioner Exam practice exam has been updated to reflect the most recent questions from the PRINCE2 PRINCE2-Practitioner Exam.

  • Demo

    Try before you buy! Get a free demo of our PRINCE2 Certification exam dumps and see the quality for yourself. Need help? Chat with our support team.

  • Validity

    Our PRINCE2 PRINCE2-Practitioner PDF contains expert-verified questions and answers, ensuring you're studying the most accurate and relevant material.

  • Success

    Achieve PRINCE2-Practitioner success! Our PRINCE2 Practitioner Exam exam questions give you the preparation edge.

If you have any question then contact our customer support at live chat or email us at support@dumps4free.com.