Question # 1
What is one step when determining initial team capacity during PI Planning? |
A. Add together all of the points from recently completed Features | B. Compare final team capacity across all teams | C. Ensure Product Owner/Product Manager approval for all time-based capacity adjustments | D. Subtract one point for every team member's vacation day, public holiday, or training day |
D. Subtract one point for every team member's vacation day, public holiday, or training day
Explanation:
One step when determining initial team capacity during PI Planning is to subtract one point for every team member’s vacation day, public holiday, or training day. This step helps the team to adjust their capacity based on the actual availability of each team member for the upcoming Program Increment (PI)1. By accounting for the time-based capacity adjustments, the team can plan their work more realistically and avoid overcommitting or underdelivering2.
References:
•PI Planning - Scaled Agile Framework
•How to Improve Your Agile Team’s Capacity Planning - Method
Question # 2
What is one responsibility of the Product Owner during Team Sync? |
A. To add new work into the Iteration | B. To clarify Story intent | C. To facilitate the event | D. To relay Customer feedback |
B. To clarify Story intent
Explanation:
One responsibility of the Product Owner during Team Sync is to clarify the intent behind each user story or backlog item. This includes providing additional context, details, and answering any queries raised by the development team1. The Team Sync is a daily event where the members of the Agile team synchronize their work and plan for the next 24 hours2. The Product Owner participates in the Team Sync to ensure that the team is working on the right things and that the stories are aligned with the customer and stakeholder needs3.
References:
•What is one responsibility of the Product Owner during Team sync …
•Team Sync - Scaled Agile Framework
•What’s a Product Owner to Do – PO role within SAFe
Question # 3
What are the minimum requirements for a Feature? |
A. Acceptance criteria, data models, and priority | B. Name, benefit hypothesis, and acceptance criteria | C. Benefit hypothesis, acceptance criteria, and priority | D. Non-functional requirements, data models, and architecture |
B. Name, benefit hypothesis, and acceptance criteria
Explanation:
The minimum requirements for a feature are a name, a benefit hypothesis, and acceptance criteria12. A name is a brief and descriptive phrase that summarizes the feature. A benefit hypothesis is a statement that describes the expected outcome and value of the feature for the customer or user. Acceptance criteria are a set of conditions that the feature must satisfy to be accepted by the customer or stakeholder12.
Some additional information that might be helpful for you are:
•The other options (A, C, and D) are not the minimum requirements for a feature, but rather additional or optional elements that may be included in the feature definition.
•Data models are representations of the data structures and relationships that the feature requires or affects. Data models are not mandatory for a feature, but they may be useful for complex or data-intensive features3.
•Priority is the relative importance or urgency of a feature compared to other features. Priority is not a requirement for a feature, but it is a factor that influences the feature selection and sequencing4.
•Non-functional requirements (NFRs) are system qualities that guide the design of the solution and often serve as constraints across the relevant backlogs. NFRs are not specific to a feature, but they may affect the feature implementation or testing5.
•Architecture is the design and structure of the system that supports the solution. Architecture is not a requirement for a feature, but it is an enabler that facilitates the feature delivery.
Question # 4
What is a pattern for splitting Features into Stories? |
A. Tasks to complete | B. Variations in data | C. Team skills | D. Layers of the technology stack |
B. Variations in data
Explanation:
A pattern for splitting Features into Stories is to use variations in data, which means identifying different types of data that the feature can handle and creating a story for each type. For example, a feature that allows users to upload files can be split into stories for different file formats, sizes, or sources. This way, the stories are independent, testable, and valuable12
References:
•Story - Scaled Agile Framework
•User stories splitting by data variations and interfaces
Question # 5
Which Agile Team event supports relentless improvement? |
A. Inspect and Adapt | B. System Demo | C. Iteration Retrospective | D. Team Sync |
C. Iteration Retrospective
Explanation:
The iteration retrospective is an Agile Team event that supports relentless improvement by allowing the team to reflect on the iteration just completed and to derive new ideas to improve the team’s process12. This reflection helps instill the concept of relentless improvement—one of the pillars of the SAFe House of Lean3—in the individuals and the team.
References:
•Iteration Retrospective - Scaled Agile Framework
•SAFe POPM 5 Flashcards | Quizlet
•SAFe Lean-Agile Principles - Scaled Agile Framework
Question # 6
What is one method for designing the end-to-end Customer experience? |
A. Journey mapping | B. Whole-product thinking | C. Feature storming | D. Persona development |
A. Journey mapping
Explanation:
Journey mapping is one method for designing the end-to-end customer experience. It is a visual representation of the steps, emotions, and pain points that a customer goes through when interacting with a product or service. It helps to identify the customer needs, expectations, and goals, as well as the gaps and opportunities for improvement in the current experience. Journey mapping also helps to align the stakeholders on the customer perspective and prioritize the features and solutions that will deliver the most value and satisfaction123
References:
•The expanding role of design in creating an end-to-end customer experience
•End to End Customer Experience: Know and Control its 3 Elements - HEFLO BPM
•How Design thinking Can Shape end to end Customer Experience
Question # 7
What is one strategy for managing complex critical path challenges? |
A. Adjust work between teams or split Features and Stories | B. Distribute work to other teams | C. Sequence work to eliminate same Iteration dependencies | D. Allocate work between teams based on forecasted capacity |
A. Adjust work between teams or split Features and Stories
Explanation:
One strategy for managing complex critical path challenges is to adjust work between teams or split Features and Stories. Complex critical path challenges are situations where the delivery of value depends on the completion of multiple interdependent tasks by different teams1. These challenges can cause delays, bottlenecks, and inefficiencies in the value stream. To overcome these challenges, one option is to adjust work between teams or split Features and Stories, so that the dependencies are minimized or eliminated2. This can help improve the flow of work, reduce the risk of integration issues, and increase the flexibility and responsiveness of the teams3.
References:
•Accelerating Flow with SAFe - Scaled Agile Framework
•Managing Dependencies - Scaled Agile Framework
Question # 8
What is one tool that visualizes Features representing a workflow? |
A. Team Kanban | B. Story Maps | C. User Experience Design | D. Continuous Delivery Pipeline |
B. Story Maps
Explanation:
A story map is a tool that visualizes features representing a workflow. A story map is a two-dimensional arrangement of user stories that shows the relationship between the user activities and the features that support them1. A story map helps the team to understand the user journey, prioritize the features based on value and dependencies, and plan the releases and iterations2.
References:
•Story Mapping - Scaled Agile Framework
•What is User Story Mapping? | Definition and Overview
Question # 9
Which of the following statements is one of the five Lean Thinking principles? |
A. Decentralize decision-making | B. Customer collaboration over contract negotiation | C. Identify the Value Stream for each product | D. Deliver working software frequently |
C. Identify the Value Stream for each product
Explanation:
Identifying the Value Stream for each product is one of the five Lean Thinking principles proposed by Womack and Jones in 1996. A value stream is the sequence of activities that deliver value to the customer, from the initial request to the final delivery1. Identifying the value stream for each product helps to eliminate waste, optimize flow, and increase customer satisfaction2.
References:
•The Five Principles of Lean - Project Management Institute
•Value Streams - Scaled Agile Framework
Question # 10
Which role ensures that the ART has the Vision and Backlog needed to engage in PI Planning successfully? |
A. Lean-Agile Center of Excellence | B. Release Train Engineer | C. Product Owner | D. Product Management |
D. Product Management
Explanation:
Product Management is the role that ensures that the Agile Release Train (ART) has the Vision and Backlog needed to engage in PI Planning successfully. Product Management is responsible for defining and communicating the Vision, which describes the future state of the solution and its features1. Product Management also develops and maintains the Program Backlog, which contains the features and enablers that the ART will implement in the upcoming Program Increments (PIs)2. Product Management collaborates with stakeholders, customers, architects, and other roles to discover, prioritize, and refine the backlog items and present them to the ART during PI Planning3.
References:
•Vision - Scaled Agile Framework
•Product Management - Scaled Agile Framework
•PI Planning - Scaled Agile Framework
Get 85 Dell Midrange Storage Solutions Design 2023 questions Access in less then $0.12 per day.
Scrum Bundle 1: 1 Month PDF Access For All Scrum Exams with Updates $100
$400
Buy Bundle 1
Scrum Bundle 2: 3 Months PDF Access For All Scrum Exams with Updates $200
$800
Buy Bundle 2
Scrum Bundle 3: 6 Months PDF Access For All Scrum Exams with Updates $300
$1200
Buy Bundle 3
Scrum Bundle 4: 12 Months PDF Access For All Scrum Exams with Updates $400
$1600
Buy Bundle 4
Disclaimer: Fair Usage Policy - Daily 5 Downloads
Dell Midrange Storage Solutions Design 2023 Exam Dumps
Exam Code: SAFe-POPM
Exam Name: Dell Midrange Storage Solutions Design 2023
- 90 Days Free Updates
- Scrum Experts Verified Answers
- Printable PDF File Format
- SAFe-POPM Exam Passing Assurance
Get 100% Real SAFe-POPM Exam Dumps With Verified Answers As Seen in the Real Exam. Dell Midrange Storage Solutions Design 2023 Exam Questions are Updated Frequently and Reviewed by Industry TOP Experts for Passing POPM Exam Quickly and Hassle Free.
Scrum SAFe-POPM Test Dumps
Struggling with Dell Midrange Storage Solutions Design 2023 preparation? Get the edge you need! Our carefully created SAFe-POPM test dumps give you the confidence to pass the exam. We offer:
1. Up-to-date POPM practice questions: Stay current with the latest exam content.
2. PDF and test engine formats: Choose the study tools that work best for you. 3. Realistic Scrum SAFe-POPM practice exam: Simulate the real exam experience and boost your readiness.
Pass your POPM exam with ease. Try our study materials today!
Prepare your POPM exam with confidence!We provide top-quality SAFe-POPM exam dumps materials that are:
1. Accurate and up-to-date: Reflect the latest Scrum exam changes and ensure you are studying the right content.
2. Comprehensive Cover all exam topics so you do not need to rely on multiple sources.
3. Convenient formats: Choose between PDF files and online Dell Midrange Storage Solutions Design 2023 practice questions for easy studying on any device.
Do not waste time on unreliable SAFe-POPM practice test. Choose our proven POPM study materials and pass with flying colors. Try Dumps4free Dell Midrange Storage Solutions Design 2023 2024 material today!
-
Assurance
Dell Midrange Storage Solutions Design 2023 practice exam has been updated to reflect the most recent questions from the Scrum SAFe-POPM Exam.
-
Demo
Try before you buy! Get a free demo of our POPM exam dumps and see the quality for yourself. Need help? Chat with our support team.
-
Validity
Our Scrum SAFe-POPM PDF contains expert-verified questions and answers, ensuring you're studying the most accurate and relevant material.
-
Success
Achieve SAFe-POPM success! Our Dell Midrange Storage Solutions Design 2023 exam questions give you the preparation edge.
If you have any question then contact our customer support at live chat or email us at support@dumps4free.com.
|