When many Scrum Teams are working on the same product, should all of their increments be
integrated every Sprint?
A.
Yes, but only for Scrum Teams whose work has dependencies.
B.
Yes, otherwise the Product Owners (and stakeholders) may not be able to accurately inspect what
is done.
C.
No, each Scrum Team stands alone.
D.
No, that is far too hard and must be done in a hardening Sprint.
Yes, otherwise the Product Owners (and stakeholders) may not be able to accurately inspect what
is done.
When can a Development Team cancel a Sprint?
A.
It can’t. Only Product Owners can cancel Sprints.
B.
When functional expectations are not well understood.
C.
When the Product Owner is absent too often.
D.
When the selected Product Backlog items for the Sprint become unachievable.
E.
When a technical dependency cannot be resolved
It can’t. Only Product Owners can cancel Sprints.
Which output from Sprint Planning provides the Development Team with a target and overarching
direction for the Sprint?
A.
The Sprint Backlog.
B.
The Sprint Goal
C.
The release plan.
D.
Sprint Review minutes
The Sprint Goal
How should a Development Team deal with non-functional requirements?
A.
Ensure every Increment meets them.
B.
Make sure the release department understands these requirements, but it is not the Development
Team’s responsibility.
C.
Handle them during the Integration Sprint preceding the Release Sprint.
D.
Assign them to the lead developers on the team.
Ensure every Increment meets them.
When is a Sprint over?
A.
When the Product Owner says it is done.
B.
When all Product Backlog items meet their definition of “Done”.
C.
When all the tasks are completed.
D.
When the time-box expires.
When the time-box expires.