Go Back on PMP Exam
Available in 1, 3, 6 and 12 Months Free Updates Plans
PDF: $15 $60

Test Engine: $20 $80

PDF + Engine: $25 $99

PMP Practice Test


Page 11 out of 76 Pages

Topic 1: Exam Pool A

A project manager for a maintenance project has a contract that is renewed annually The project started 6 years ago After contract renewal this year the auditors reported that this version of the contract violates a new law that was passed last year

What has happened in this situation?


A.

The contract has not been appropriately reviewed by the project team


B.

The stakeholder engagement plan has not been correctly implemented


C.

The legal department has not disseminated the law correctly to all staff.


D.

The project manager does not have enough knowledge on this legal matter





A.
  

The contract has not been appropriately reviewed by the project team



Explanation
According to the PMBOK Guide, the project team is responsible for conducting procurement activities, such as planning, conducting, controlling, and closing procurements. This includes reviewing and updating the contracts as needed to ensure compliance with the project requirements and the applicable laws and regulations. The project manager should also involve the legal department and other relevant stakeholders in the contract review process to avoid any potential issues or disputes. Therefore, if the contract violates a new law that was passed last year, it means that the project team has not performed an adequate review of the contract before renewing it, and has failed to identify and mitigate the risk of non-compliance.

References:
PMBOK Guide, Chapter 12, Section 12.1, Plan Procurement Management
PMBOK Guide, Chapter 12, Section 12.2, Conduct Procurements
PMBOK Guide, Chapter 12, Section 12.3, Control Procurements
PMBOK Guide, Chapter 12, Section 12.4, Close Procurements
PBA Guide, Chapter 5, Section 5.3.2, Contract Review and Approval

A team has been working on a project for several months,, but the completion date is unclear because the scope is changing frequently as new knowledge is gained. Some deliverables have already been completed, but when new stakeholders join the team, they complain that project outcomes are not meeting business goals.

How can the project manager prevent this situation from happening in the future?


A.

Create a prioritized backlog and define iteration review sessions with stakeholders


B.

Create a detailed work breakdown structure (WBS) and milestone schedule approved by all stakeholders


C.

Schedule a daily meeting to review team performance and impediments


D.

Schedule a kick-off meeting for every project phase to share the project management plan with all stakeholders





A.
  

Create a prioritized backlog and define iteration review sessions with stakeholders



According to the Agile Practice Guide, a prioritized backlog is a list of features, functions, requirements, enhancements, and fixes that are prioritized according to the value they deliver to the customer and the amount of work required to complete them. A prioritized backlog helps the project team to manage changing scope and expectations in an agile environment, where new knowledge and feedback are continuously incorporated into the project. By defining iteration review sessions with stakeholders, the project manager can ensure that the project outcomes are aligned with the business goals and that the stakeholders are satisfied with the deliverables. Iteration review sessions are meetings where the project team demonstrates the work completed in an iteration and solicits feedback from the stakeholders. Iteration review sessions help to validate the value of the deliverables, identify any defects or issues, and adjust the backlog for the next iteration. References: Agile Practice Guide, pages 37-38, 5.1.1 Prioritized Backlog, 5.2.2 Iteration Review.

A company's CEO has just returned from a conference on the use of artificial intelligence (Al) and would like the project manager to implement this technology in the organization What should the project manager do first?


A.

Start developing a business case.


B.

Start a strengths, weaknesses, opportunities and threats (SWOT).


C.

Engage stakeholders and allocate resources


D.

Gather requirements from stakeholders





D.
  

Gather requirements from stakeholders



According to the PMBOK Guide, the first process in the Project Integration Management knowledge area is Develop Project Charter. This process authorizes the project and defines the high-level scope, objectives, and stakeholders of the project. The project charter is based on the business case, which is the document that justifies the need and value of the project. The business case is usually prepared by the project sponsor or initiator, not the project manager. Therefore, option A is incorrect. Option B is also incorrect, because a SWOT analysis is a technique used to identify the project risks, assumptions, and constraints, which are part of the project planning process, not the initiating process. Option C is incorrect, because engaging stakeholders and allocating resources are also part of the project planning and executing processes, not the initiating process. Option D is the correct answer, because gathering requirements from stakeholders is a key activity in the initiating process group, as it helps to define the scope and objectives of the project, as well as the expectations and needs of the stakeholders. The project manager should gather requirements from stakeholders before developing the project charter, as the charter should reflect the stakeholder requirements and align with the business case. References: = PMBOK Guide, 6th edition, pages 30-33, 75-77, 123-125, 135-137.

An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)


A.

Ask the stakeholders about the priority of this change


B.

Ask the product owner to review the product backlog


C.

Ask the team members to analyze the impact of this change


D.

Ask the sponsor to approve the change request


E.

Ask the team members to include the change in the next iteration





A.
  

Ask the stakeholders about the priority of this change



B.
  

Ask the product owner to review the product backlog



In an agile project, the project manager should collaborate with the stakeholders and the product owner to manage changes in the product. Asking the stakeholders about the priority of this change will help the project manager understand the value and urgency of the change, and align the expectations of the stakeholders with the project vision. Asking the product owner to review the product backlog will help the project manager ensure that the change is properly prioritized and incorporated into the product backlog, which is the source of requirements for the agile project. Asking the team members to analyze the impact of this change, asking the sponsor to approve the change request, or asking the team members to include the change in the next iteration are not the best actions to take in an agile project, as they may introduce unnecessary delays, bureaucracy, or scope creep. References: = PMBOK Guide, 6th edition, page 18, section 1.2.3 (Agile Considerations); page 176, section 5.1.1.1 (Project Stakeholders); page 179, section 5.1.3.1 (Project Charter); page 181, section; (Product Owner); page 182, section 2.3.1 (Product Backlog)

During an ongoing project a key resource asks the project manager about the project purpose and if it is aligned with the organization's strategy What should the project manager share with the key resource?


A.

The updated benefits management plan


B.

The updated scope management plan


C.

The updated project management plan


D.

The updated communications management plan





C.
  

The updated project management plan



The project manager should share the updated project management plan with the key resource, as it contains the information about the project purpose and alignment with the organization’s strategy. The project management plan is the primary source of guidance for the project team and stakeholders, and it integrates all the subsidiary plans and baselines, such as the benefits management plan, the scope management plan, and the communications management plan. By sharing the updated project management plan, the project manager can ensure that the key resource understands the project objectives, scope, benefits, risks, assumptions, and constraints, as well as the communication channels and methods for the project. 

References: (Professional in Business Analysis Reference Materials source and documents)
PMBOK Guide, 6th edition, section 4.2.3.1, page 89 
PMP Exam Prep, 10th edition, Rita Mulcahy, page 78 
PMP Practice Questions #58 - iZenBridge1


Page 11 out of 76 Pages
Previous