When are acceptance tests typically written for a user story?
A.
After coding the story, but before user acceptance testing begins
B.
After writing the story, but before coding begins
C.
At the start of Product Backlog prioritization planning
D.
After estimating the Product Backlog, but before Sprint planning begins
At the start of Product Backlog prioritization planning
Velocity is the:
A.
total number of Product Backlog hours completed in an iteration divided by the number
of developers.
B.
measured rate at which teams turn Product Backlog items into running, tested features.
C.
measured rate at which the project manager turns the Product Backlog into tested
features.
D.
total number of Product Backlog hours completed when developers work in pairs.
measured rate at which teams turn Product Backlog items into running, tested features.
A development team has finished identifying the tasks they will be accountable for during
the next sprint. Which of the following tools best provides transparency into the progress
throughout the sprint?
A.
Burndown chart
B.
Gantt chart
C.
Hours expended chart
D.
Management baseline chart
Burndown chart
Following chart lists stories for a release of an Agile project;
If the team completes Story A, Story B, and 50% of Story C for the first iteration, what is the team's velocity?
A.
9
B.
10
C.
12
D.
15
9
Which of the following would be most likely to assist when a customer has difficulty
prioritizing stories?
A.
Split the stories into smaller ones to allow the customer to choose the pieces that they
want.
B.
Have the team provide guidance into where their priorities lie to the customer.
C.
Provide additional technical details to give the customer insight into technical
challenges.
D.
Have the team rewrite the stories with additional details to clarify requirements.
Split the stories into smaller ones to allow the customer to choose the pieces that they
want.