In eXtreme Programming (XP), analysis, design, coding, and testing phases are done:
A.
At the beginning of the iteration.
B.
Every day.
C.
In sequence.
D.
Without documentation.
Every day.
User stories are temporary artifacts.They are considered relevant until the:
A.
Team completes them.
B.
End of the project.
C.
Release is complete.
D.
End of the sprint.
Team completes them.
The term ¡°last responsible moment¡± refers to the moment at which:
A.
the iteration testing deadline arrives and code testing must stop.
B.
failing to make a decision eliminates an important alternative.
C.
release planning is complete and the first iteration planning starts.
D.
the implementation date is set and sponsor approval has been received.
failing to make a decision eliminates an important alternative.
In a Lean Software Development environment, the Project Leader strives to eliminate:
A.
Work in Process (WIP) and bugs.
B.
Delays and building what is not needed.
C.
Defects and features with low value stream values.
D.
Poor requirements and changing scope.
Defects and features with low value stream values.
What do project reports show during the Sprint review meeting?
A.
Estimates compared to the baseline
B.
Actual results to the plan
C.
Return on investment (ROI)
D.
Earned value measurement (EVM)
Return on investment (ROI)