A common estimation unit for Agile projects is:
A.
Lines of code.
B.
Function points
C.
Story points.
D.
Use-case points.
Story points.
The smallest amount of functionality that delivers customer value is best described as a:
A.
Function point analysis.
B.
Right sized story.
C.
Minimum marketable feature.
D.
Userstory map.
Minimum marketable feature.
When facilitated and managed well, the primary benefits of a project retrospective should
be to:
A.
Increase empowerment and enjoyment for the team.
B.
Identify the most important issues for the sponsors.
C.
Provide an open forum for team member complaints.
D.
Allow the team to get ahead on release planning.
Allow the team to get ahead on release planning.
Scrum practices are facilitated by the:
A.
ScrumMaster.
B.
Product Owner.
C.
Project Sponsor.
D.
Scrum team.
ScrumMaster.
Project managers use velocity to determine:
A.
If the team is committing to an appropriate amount of work for the iteration.
B.
How much work each team member is capable of completing during an iteration.
C.
How much work teams that are similar in size are capable of completing during an
iteration.
D.
If the Product Owner is prioritizing work appropriately in preparation for iteration
planning.
If the team is committing to an appropriate amount of work for the iteration.