A development team has finished identifying the tasks they will be accountable for during
the next sprint.Which of the following tools best provides transparency into the progress
throughout the sprint?
A.
Burndown chart
B.
Gantt chart
C.
Hours expended chart
D.
Management baseline chart
Burndown chart
The purpose of the iteration retrospective is to:
A.
Report progress of the work effort, what work will be done next, and review impediments
to progress.
B.
Prioritize the Product Backlog, generate development and testing estimates, and plan
the next iteration.
C.
Provide a demonstration of the features developed during the iteration, get feedback
from users, and begin testing.
D.
Identify what worked well, what did not work well, and what actions should be taken to
improve the process.
Identify what worked well, what did not work well, and what actions should be taken to
improve the process.
For the best results in an Agile project, customers should:
A.
set priorities and identify product features.
B.
interview new team members for fit.
C.
approve development plans and tasks.
D.
set sprint and release schedules.
set priorities and identify product features.
Which best describes the attributes of the IN VEST criteria in a user story?
A.
Incremental, Net, Variation, Exceed, Scope, and Training
B.
Interdependent, Nonfunctional, Value, Exploratory, Sprint, and Timebox
C.
Innovation, Nested, Vision, Estimating, Scalable, and Team
D.
Independent, Negotiable, Valuable, Estimable, Small, and Testable
Independent, Negotiable, Valuable, Estimable, Small, and Testable
Which technique is used by a project team to estimate the amount of work that can be
done per iteration?
A.
Velocity measurement
B.
Relative prioritization
C.
Planning Poker
D.
Release planning
Velocity measurement