An software engineer is applying new updates to a program in a sandbox environment. Which of the following risk strategies best describes this practice?


A. Transfer


B. Mitigate


C. Avoid


D. Accept





B.
  Mitigate

Explanation: Mitigate is a risk strategy that involves taking actions to reduce the probability or impact of a risk. By applying new updates to a program in a sandbox environment, the software engineer is testing the changes before implementing them in the actual system, thus minimizing the chance of errors or failures that could affect the project1.

A project manager is organizing and running a project closure meeting. Which of the following best describes the objective of this meeting?


A. To move the system to a production environment


B. To obtain project sign-off


C. To formalize the end of the contract


D. To release resources





B.
  To obtain project sign-off

Explanation: A project closure meeting is a formal gathering held at the end of a project timeline. Its chief purpose is to evaluate the project’s performance, identify and discuss the achieved outcomes, successes, and challenges, and confirm that all predefined tasks and objectives have been completed successfully1. The project closure meeting also involves obtaining project sign-off from all necessary parties, such as the project sponsor, the client, the stakeholders, and the team members. Project sign-off is the official approval that the project has met the agreed-upon criteria and quality standards, and that the project is formally closed2.

A new project has been assigned to a project manager. In order to move forward with the project charter, which of the following should the project manager work with to define the success criteria for the initiative?


A. Lead architect


B. Project sponsor


C. Program manager


D. Scrum master





B.
  Project sponsor

A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?


A. Multiauthoring software


B. Word processor


C. Real-time polling


D. Conferencing platforms





A.
  Multiauthoring software

Explanation: The project manager is using multiauthoring software to maintain the version control for the documentation of requirements. Multiauthoring software is a type of software that allows multiple users to create, edit, and collaborate on documents simultaneously. It also provides features such as tracking changes, commenting, reviewing, and merging versions. Multiauthoring software can help to improve the quality, accuracy, and consistency of documents and facilitate communication and feedback among stakeholders. Examples of multiauthoring software include Google Docs, Microsoft Word Online, and Confluence34

An institution wants to implement software solutions to help manage the internal flow for formally responding in writing to citizens' complaints. Which of the following solutions would be BEST?


A. Enterprise resource planning and end user applications


B. Electronic document and record management systems


C. Customer relationship management and databases


D. Content management and financial systems





B.
  Electronic document and record management systems

Explanation: Electronic document and record management systems would be the best software solutions to help an institution manage the internal flow for formally responding in writing to citizens’ complaints. Electronic document and record management systems are software systems that help organizations create, store, organize, manage, track, and distribute electronic documents and records. Electronic document and record management systems can help to improve efficiency, productivity, collaboration, compliance, and security of document and record management processes and workflows.