A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?
A. Responsibility assignment matrix
B. Acceptable communication channels
C. Risk registry
D. Staff directory
Which of the following provides a layered approach to logging in to systems that contain an organization's most valuable intellectual property?
A. Remote access
B. Password protection
C. Multifactor authentication
D. Virtual private network
Which of the following is a capital expense?
A. Building lease
B. Building purchase
C. Building maintenance
D. Building insurance
Explanation: A capital expense is the cost of acquiring or making improvements to fixed assets that have a useful life of more than one year1. A building purchase is an example of a capital expense, as it is a long-term investment that increases the value of the company’s assets2. Building lease, maintenance, and insurance are not capital expenses, as they are recurring or short-term costs that do not increase the value of the company’s assets3.
A piece of equipment has malfunctioned and is stalling the completion of a deliverable for a project. Which of the following should the project manager do next?
A. Buy a replacement for the faulty equipment.
B. Get the maintenance team to resolve the issue.
C. Escalate the issue to the project sponsor.
D. Rate the severity of the impact the issue has on the project.
Which of the following is the most important activity for the project manager during the closure of a project?
A. Obtain project sign-off.
B. Capture lessons learned.
C. Document historical information.
D. Release resources.
Page 4 out of 58 Pages |
Previous |