A PM wants to add a chart to the monthly status report to show major accomplishments for key events. Which of the following is the best chart to use?
A. Milestone
B. Gantt
C. Burndown
D. PERT
A sponsor prefers to communicate with the team using email, phone calls, conversations in the hallway, and impromptu meetings. Which of the following types of communication is the sponsor using?
A. Informal communication
B. Formal communication
C. Synchronous communication
D. Asynchronous communication
Explanation: Informal communication is a type of communication that is casual, spontaneous, and unstructured. It does not follow any predefined rules, protocols, or formats. Examples of informal communication include email, phone calls, conversations in the hallway, and impromptu meetings12. The sponsor is using informal communication to communicate with the team, as these methods are convenient, flexible, and personal. However, informal communication may also have some drawbacks, such as lack of documentation, inconsistency, and potential for misunderstanding3. Therefore, the sponsor should also use formal communication when necessary, such as for official reports, contracts, and presentations4.
Which of the following software programs would be best to use to store information related to business transactions?
A. Record management system
B. Customer relationship management
C. Enterprise resource planning
D. Content management system
Explanation: Enterprise resource planning (ERP) software is a type of software that integrates various business functions and processes, such as accounting, finance, inventory, sales, purchasing, human resources, and more. ERP software helps businesses store, organize, and manage information related to business transactions, such as invoices, payments, orders, receipts, and reports. ERP software also provides real-time data analysis, reporting, and forecasting capabilities12.
Which of the following activities would a project manager perform during the closing phase? (Select THREE).
A. Lessons learned
B. Risk analysis
C. Removing resources
D. Acquiring resources
E. Statement of work sign-off
F. Stakeholder analysis
G. Removing access
Explanation: Lessons learned, removing resources, and removing access are activities that a project manager would perform during the closing phase of a project. Lessons learned is a process of collecting and documenting the knowledge and experience gained from a project for future reference and improvement. Removing resources is a process of releasing or reallocating any human or material resources that were used for the project. Removing access is a process of revoking any permissions or privileges that were granted to the project team members or stakeholders for accessing any systems or data related to the project. These activities can help to finalize and close a project successfully and ensure that all deliverables are transferred, all documentation is approved and archived, all contracts are closed, and all stakeholders are satisfied.
A project manager is eager to define access requirements during the initiation phase of a project. Which of the following steps should the project manager perform first?
A. Define the WBS.
B. Develop a RAM.
C. Manage the vendors.
D. Assess the resource pool.