During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?


A. Pareto chart


B. Milestone chart


C. Burndown chart


D. Gantt chart





C.
  Burndown chart

After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?


A. Continuous integration


B. Rollback plan


C. Customer notification


D. Automated testing





C.
  Customer notification

A PM is working to establish accepted communication channels and to define access requirements. In which of the following phases is the project?


A. Discovery


B. Execution


C. Initiating


D. Planning





D.
  Planning

A procurement team analyzes solutions submitted from multiple vendors for the upcoming release of a required development service. The procurement team identifies a potential partnership. Which of the following would the procurement team most likely request?


A. Quote


B. Information


C. Proposal


D. Bid





C.
  Proposal

Explanation: A proposal is a detailed document submitted by vendors outlining how they will meet project requirements. It helps in assessing vendor solutions and suitability, consistent with CompTIA Project+ procurement and vendor management practices.

Which of the following should be considered first when determining the privacy management for project data?


A. Evaluating the current privacy protection program


B. Understanding applicable privacy regulations


C. Maintaining awareness of industry best practices


D. Implementing security role-based controls





B.
  Understanding applicable privacy regulations

Explanation: Before starting a new project that involves personal data, the project manager should first understand the relevant privacy regulations that apply to the data subjects, the data controllers, and the data processors. These regulations may vary depending on the location, industry, and nature of the data. For example, GDPR applies to any project that processes the personal data of individuals in the European Union, regardless of where the project is based or executed. Understanding the applicable privacy regulations will help the project manager to identify the legal obligations, risks, and compliance requirements for the project data. References = CompTIA Project+ Study Guide, Chapter 3: Project Planning, Section 3.4: Data Privacy and Security, p. 121-122; A Project Management Approach to Data Protection Compliance; 10 Data Protection Considerations Before Starting a New Project; Project Teams Must Manage Risk and New Requirements to Ensure Data Privacy