Discount Offer
Go Back on PK0-005 Exam
Available in 1, 3, 6 and 12 Months Free Updates Plans
PDF: $15 $60

Test Engine: $20 $80

PDF + Engine: $25 $99



Pass exam with Dumps4free or we will provide you with three additional months of access for FREE.

PK0-005 Practice Test


Page 13 out of 58 Pages

Which of the following is a consideration when determining a project's ESG factors?


A. Project management methodology


B. IT infrastructure security


C. Proper accounting practices


D. Corporate values compliance





D.
  Corporate values compliance

Explanation: Corporate values compliance is a consideration when determining a project’s ESG factors, because it reflects how a project aligns with the ethical standards and social responsibility of the organization. Corporate values compliance can help to enhance the reputation, trust, and loyalty of the organization among its stakeholders, as well as to avoid legal or regulatory issues that may arise from violating the values. Corporate values compliance can also influence the project scope, objectives, deliverables, and stakeholders, as well as the project management methodology, processes, and practices. The other options are not directly related to ESG factors. Project management methodology is the approach or framework that guides how a project is planned, executed, monitored, and controlled. IT infrastructure security is the protection of the hardware, software, network, and data components of a project from unauthorized access, use, modification, or destruction. Proper accounting practices are the rules and standards that govern how financial transactions and statements are recorded, reported, and audited for a project.

Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?


A. Remove the team member's access.


B. Release the project resources.


C. Collect the stakeholders' feedback.


D. Have the closeout report approved.





B.
  Release the project resources.

The quarterly financial report displays losses from a project even though the project was completed successfully several weeks ago. Which of the following actions should the project manager perform next?


A. Remove access.


B. Complete the project sign-off.


C. Release the resources.


D. Outline the lessons learned.





B.
  Complete the project sign-off.

Explanation: The project sign-off is the formal acceptance of the project deliverables by the client, stakeholder, or customer. It also marks the closure of the project and the release of the final payment. If the project sign-off is not completed, the project may still incur costs and liabilities, which can explain the losses in the financial report. Therefore, the project manager should complete the project sign-off as soon as possible to avoid further losses12.

A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?


A. 9 days and $3,000


B. 10 days and $3,200


C. 12 days and $3,800


D. 14 days and $4,000





B.
  10 days and $3,200

Explanation: The total amount that should be budgeted for the task is calculated by adding the expected value of the risk to the original estimate. The expected value of the risk is the product of the probability and the impact of the risk. In this case, the expected value of the risk is 0.2 x (5 days and $1,000) = 1 day and $200. Therefore, the total amount that should be budgeted for the task is 9 days and $3,000 + 1 day and $200 = 10 days and $3,2001.

A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project's closure. Which of the following would have most likely prevented the data from being stolen?


A. Removing access


B. Closing contracts


C. Project sign-off


D. Project evaluation





A.
  Removing access

Explanation: Removing access means revoking the contractor’s permissions to access the project data, systems, and devices after the project is closed. This is a crucial security measure to prevent unauthorized access, misuse, or theft of sensitive data by external parties. Closing contracts, project sign-off, and project evaluation are important steps in the project closure process, but they do not necessarily prevent data theft by themselves. They may involve formal agreements, documentation, and feedback, but they do not address the technical aspects of data security. References = CompTIA Project+ Study Guide: Exam PK0-005, Third Edition, Chapter 14: Closing the Project, page 3771; 9 Ways to Prevent Third-Party Data Breaches in 20232; 3 Ways to Prevent Data Theft by Contractors3


Page 13 out of 58 Pages
Previous