Topic 12: Scenario 7 "Test Estimation"

Identify THREE items that would be part of the work-breakdown structure showing the key
testing activities for the acceptance test project. 2 credits (for 2 out of 3 correct 1 credit)


A.

A. Test planning, test case preparation and test execution for each of the four iterations


B.

B. Work should be explicitly allocated to test completion, test management, installation and
to training on using the system


C.

C. Activities to deploy the system in the user environ


D.

Regression testing in the second, third and fourth iterations


E.

 Development activities for unit and integration testing


F.

Reviews on requirements documentation


G.

Defining test environment requirements for system testing





A.
  

A. Test planning, test case preparation and test execution for each of the four iterations



B.
  

B. Work should be explicitly allocated to test completion, test management, installation and
to training on using the system



D.
  

Regression testing in the second, third and fourth iterations



Model characteristics:
Which THREE of the below mentioned characteristics relate to TMMi? 1 credit


A.

5 maturity levels


B.

 Focussed on higher level testing


C.

20 key areas


D.

Highly related to CMMI


E.

Continuous model


F.

taged model


G.

Focussed on component and integration testing


H.

Is build around 12 critical testing processes





A.
  

5 maturity levels



D.
  

Highly related to CMMI



F.
  

taged model



The test improvement project will take place in an organization developing a safety-critical
avionics application. Which one of the following standards do you believe would be most
appropriate to take into account for compliance during your assignment? 1 credit


A.

 ISO 9126


B.

IEEE 829


C.

BS 7925/2


D.

DO-178B





D.
  

DO-178B



A test assessment has been carried out using the selected model as a reference
framework. A number of recommendations have been identified and you are asked to
prioritize them. Based on your knowledge of the project, you are expecting severe
resistance to change. Which of the following would be the most important selection criterion
for defining the priority of the recommendations? 2 credits


A.

Synchronized with the overall long-term organizational strategy


B.

Defined according to the maturity model used


C.

Most visible to stakeholders


D.

Low costs actions first





C.
  

Most visible to stakeholders



Comparing TMMi and TPI, which is not a valid reason for choosing either TPI or TMMi? 2
credits


A.

If the scope of test performance improvement covers all test levels, TMMi is preferred
since TPI focusses mainly on black-box testing.


B.

If the organization is already applying CMMI, TMMi may be preferred since it has the
same structure and uses the same terminology. TMMi addresses management
commitment very strongly and is therefore more suitable to support a top-down
improvement process.


C.

TPI is much more a bottom-up model that is suitable for addressing test topics for a
specific (test) project.


D.

 TMMi can only be used with the traditional V model,whereas TPI can be used with all
types of software life cycles.





D.
  

 TMMi can only be used with the traditional V model,whereas TPI can be used with all
types of software life cycles.