Topic 18: Scenario 10, V3 "Online Application"
Why might a RAD approach be a better option for the test manager rather than a
sequential development? 2 credits
A.
It will extend the development team’s abilities and enhance future delivery capabilities.
B.
It will allow the marketing, clerical and testing staff to validate and verify the early screen
prototypes.
C.
Time-box constraints will guarantee code releases are delivered on schedule.
D.
More time can be spent on test execution as less formal documentation is required.
It will allow the marketing, clerical and testing staff to validate and verify the early screen
prototypes.
Which of the following is NOT a typical key challenge for testing in a RAD based
development approach? 1 credit
A.
Re-usable test scripts for (automated) regression testing
B.
Project management and control
C.
No complete requirements specification
D.
Time-boxing
Project management and control
The business has asked for a weekly progress report. Which of the following would be
appropriate as a measure of test coverage? 2 credits
A.
Percentage of business requirements exercised
B.
Percentage of planned hours worked this week
C.
Percentage of countries that have test scenarios
D.
Percentage of test iterations completed
Percentage of business requirements exercised
As a result of the RAD based development approach, the test manager has decided to
change the risk mitigation approach. Which test technique might be most appropriate to
use? 2 credits
A.
Decision Table Testing
B.
Boundary Value Analysis
C.
Error Guessing
D.
Exploratory Testing
Exploratory Testing
Regarding the process described above, what is the most important recommendation you
would make using IEEE 1044 as a guide? 2 credits
A.
No priority or severity assigned
B.
Incident numbering is manual rather than automated
C.
No mentioning of reproduceability
D.
No classification on type of incident
No priority or severity assigned