What is the primary responsibility of the Scrum Master?
A.
To Prioritize the Product Backlog
B.
To remove any impediments the Development Team encounters during their work
C.
To work with the Product Owner to develop the Product Backlog
D.
To manage the Development Team
To remove any impediments the Development Team encounters during their work
Which of the following might the Scrum Team discuss during a Sprint Retrospective?
A.
Methods of communication
B.
The way the Scrum Team does Sprint Planning
C.
Skills needed to improve the Development Team's ability to deliver
D.
Its Definition of Done
E.
All of the above
All of the above
Which of the following is not a Scrum artifact?
Qual dos seguintes não é um artefato Scrum?
A.
User Stories
B.
Sprint Backlog
C.
Product Backlog
D.
Incremento de Software
User Stories
Which three questions are answered by all Development Team members at the Daily
Scrum?
A.
What work am I going to do today?
B.
Why were you late?
C.
What impediments are in the way of my accomplishing my work?
D.
What work did I do yesterday?
E.
How is the Sprint proceeding?
What work am I going to do today?
What impediments are in the way of my accomplishing my work?
What work did I do yesterday?
The Sprint planning meeting is comprised of how many sections?
A.
4
B.
3
C.
2
D.
1