Amy is the project manager for her company. In her current project the organization has a
very low tolerance for risk events that will affect the project schedule. Management has
asked Amy to consider the affect of all the risks on the project schedule. What approach
can Amy take to create a bias against risks that will affect the schedule of the project?


A.

She can filter all risks based on their affect on schedule versus other project objectives.


B.

She can have the project team pad their time estimates to alleviate delays in the project
schedule


C.

She can shift risk-laden activities that affect the project schedule from the critical path as
much a possible.


D.

She can create an overall project rating scheme to reflect the bias towards risks that
affect the project schedule.





D.
  

She can create an overall project rating scheme to reflect the bias towards risks that
affect the project schedule.



Which types of project tends to have more well-understood risks?


A.

First-of-its kind technology projects


B.

State-of-art technology projects


C.

Recurrent projects


D.

Operational work projects





C.
  

Recurrent projects



Robert is the business analyst for his organization and he's working with several
stakeholders to identify the business need for an opportunity. Robert needs to identify the
stakeholder that will be responsible for authorizing the actions needed in order to meet the
identified business need. Which stakeholder does Robert need to identify?


A.

Regulator


B.

Implementation Subject Matter Expert


C.

Sponsor


D.

Customer





C.
  

Sponsor



Which of the following processes is responsible for low risk, frequently occurring low cost changes?


A.

Incident Management


B.

IT Facilities Management


C.

Release Management


D.

Request Fulfillment





D.
  

Request Fulfillment



Which of the following types of IT organizational structures states that all IT resources are
centralized under a single reporting structure with centralized resource allocation (staffing),
and the organizational structure is built around the resource pools?


A.

Federated


B.

Centralized


C.

Project-based


D.

Decentralized





C.
  

Project-based