Topic 1: Volume A
You work as a project manager for TechSoft Inc. You are working with the project
stakeholders on the qualitative risk analysis process in your project. You have used all the
tools to the qualitative risk analysis process in your project. Which of the following
techniques is NOT used as a tool in qualitative risk analysis process?
A.
Risk Data Quality Assessment
B.
Risk Categorization
C.
Risk Reassessment
D.
Risk Urgency Assessment
Risk Reassessment
Paul has been asked to complete SWOT analysis for his solution scope. What does SWOT analysis mean?
A.
Stakeholder Weaknesses, Organizational Threats
B.
Strengths, Weaknesses, Opportunities, Threats
C.
Strengths, Weaknesses, Opportunities, Time
D.
Stakeholders Weaknesses, Organization, Threats
Strengths, Weaknesses, Opportunities, Threats
Marsha is the project manager of the NHQ Project. There's a risk that her project team has
identified, which could cause the project to be late by more than a month. Marsha does not
want this risk event to happen so she devises extra project activities to ensure that the risk
event will not happen. The extra steps, however, will cost the project an additional $10,000.
What type of risk response is this approach?
A.
Exploiting
B.
Transference
C.
Mitigation
D.
Enhancing
Mitigation
Which of the following essential elements of IT Portfolio Investment Management drives
better decisions by providing real-time portfolio performance information in personalized
views, such as cost/benefit summary, risk versus reward, ROI versus alignment, and
balance bubble charts?
A.
Workflow, Process Management, Tracking and Authorization
B.
Portfolio Management
C.
Integrated Dashboards and Scorecards
D.
Portfolio What-If Planning
Integrated Dashboards and Scorecards
Which of the following essential elements of IT Portfolio Investment Management enables
portfolio managers to include or exclude investments, change start and end dates, adjust
budgets and reevaluate priorities?
A.
Integrated Capability
B.
Portfolio Planning Analysis
C.
Portfolio What-If Planning
D.
Portfolio Management
Portfolio What-If Planning