Listening to what is being said by all members of a group or audience and then summarizing or interpreting is called______________.


A. Directive listening


B. Non-listening


C. Visual listening


D. Facilitative listening





D.
  Facilitative listening

What relationship more accurately defines a situation model of parallel activities that require a partial start of one activity?


A. Start to start


B. Star to finish


C. Finish to start


D. Finish to finish





A.
  Start to start

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following is NOT an advantage of the critical path method:


A. The ability to determine cost overruns of critical path activities


B. The ability to identify activities that cannot have their schedules slip if the desired project end date is to be achieved


C. Reveals activities that additional resources need to be dedicated toward


D. The ability to show slippage in the progress of key activities





A.
  The ability to determine cost overruns of critical path activities

The process of stating goals and determining the most effective way of reaching them is the definition for:


A. Implementing


B. Mission Statement


C. Managing


D. Planning





D.
  Planning

A task has an early start of day 4. late start of day 14. early finish of day 10. and a late finish of day 20. What is the task's float?


A. 4


B. 10


C. 20


D. 9





B.
  10