Topic 1, Volume A
Which input to the Plan Risk Management process provides information on high-level risks?
A.
Project charter
B.
Enterprise environmental factors
C.
Stakeholder register
D.
Organizational process assets
Project charter
Which input may influence quality assurance work and should be monitored within the context of a
system for configuration management?
A.
Work performance data
B.
Project documents
C.
Scope baseline
D.
Requirements documentation
Project documents
Change requests are processed for review and disposition according to which process?
A.
Control Quality
B.
Control Scope
C.
Monitor and Control Project Work
D.
Perform Integrated Change Control
Perform Integrated Change Control
The review of a sellers progress toward achieving the goals of scope and quality within cost and
schedule compared to the contract is known as:
A.
Work performance information.
B.
Inspections and audits.
C.
Payment systems.
D.
Procurement performance reviews.
Procurement performance reviews.
The iterative and interactive nature of the Process Groups creates the need for the processes in
which Knowledge Area?
A.
Project Communications Management
B.
Project Integration Management
C.
Project Risk Management
D.
Project Scope Management
Project Integration Management