Go Back on CAPM Exam
Available in 1, 3, 6 and 12 Months Free Updates Plans
PDF: $15 $60

Test Engine: $20 $80

PDF + Engine: $25 $99

CAPM Practice Test


Page 8 out of 157 Pages

Topic 1, Volume A

Which process involves monitoring the status of the project to update the project costs and
managing changes to the cost baseline?


A.

Estimate Costs


B.

Control Costs


C.

Determine Budget


D.

Plan Cost Management





B.
  

Control Costs



Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying,
or rejecting changes to the project and for recording and communicating decisions?


A.

Project team


B.

Focus group


C.

 Change control board


D.

Project stakeholders





C.
  

 Change control board



Plan Schedule Management is a process in which Knowledge Area?


A.

Project Scope Management


B.

Project Human Resource Management


C.

Project Integration Management


D.

Project Time Management





D.
  

Project Time Management



An output of the Validate Scope process is:


A.

A requirements traceability matrix.


B.

The scope management plan.


C.

Work performance reports.


D.

Change requests.





D.
  

Change requests.



The Perform Integrated Change Control process occurs in which Process Group?


A.

Initiating


B.

Executing


C.

Monitoring and Controlling


D.

Planning





C.
  

Monitoring and Controlling