Topic 1, Volume A
Which process involves monitoring the status of the project to update the project costs and
managing changes to the cost baseline?
A.
Estimate Costs
B.
Control Costs
C.
Determine Budget
D.
Plan Cost Management
Control Costs
Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying,
or rejecting changes to the project and for recording and communicating decisions?
A.
Project team
B.
Focus group
C.
Change control board
D.
Project stakeholders
Change control board
Plan Schedule Management is a process in which Knowledge Area?
A.
Project Scope Management
B.
Project Human Resource Management
C.
Project Integration Management
D.
Project Time Management
Project Time Management
An output of the Validate Scope process is:
A.
A requirements traceability matrix.
B.
The scope management plan.
C.
Work performance reports.
D.
Change requests.
Change requests.
The Perform Integrated Change Control process occurs in which Process Group?
A.
Initiating
B.
Executing
C.
Monitoring and Controlling
D.
Planning
Monitoring and Controlling