Go Back on CAPM Exam
Available in 1, 3, 6 and 12 Months Free Updates Plans
PDF: $15 $60

Test Engine: $20 $80

PDF + Engine: $25 $99

CAPM Practice Test


Page 7 out of 157 Pages

Topic 1, Volume A

A project manager is appointed full-time to a project and is given full-time administrative staff and
full-time project team members. This situation describes which type of organizational structure?


A.

Projectized


B.

Weak matrix


C.

Functional


D.

Balanced matrix





A.
  

Projectized



A project charter is an output of which Process Group?


A.

Executing


B.

Planning


C.

Initiating


D.

Closing





C.
  

Initiating



Which tool or technique is effective in a project in which the deliverable is not a service or result?


A.

Inspection


B.

Variance analysis


C.

Decomposition


D.

Product analysis





D.
  

Product analysis



An element of the project scope statement is:


A.

Acceptance criteria.


B.

A stakeholder list.


C.

A summary budget,


D.

High-level risks





A.
  

Acceptance criteria.



Which document describes the necessary information to determine if a project is worth the
required investment?


A.

Cost baseline


B.

Service level agreement


C.

Memorandum of understanding


D.

Business case





D.
  

Business case




Page 7 out of 157 Pages
Previous