Topic 1, Volume A
A project manager is appointed full-time to a project and is given full-time administrative staff and
full-time project team members. This situation describes which type of organizational structure?
A.
Projectized
B.
Weak matrix
C.
Functional
D.
Balanced matrix
Projectized
A project charter is an output of which Process Group?
A.
Executing
B.
Planning
C.
Initiating
D.
Closing
Initiating
Which tool or technique is effective in a project in which the deliverable is not a service or result?
A.
Inspection
B.
Variance analysis
C.
Decomposition
D.
Product analysis
Product analysis
An element of the project scope statement is:
A.
Acceptance criteria.
B.
A stakeholder list.
C.
A summary budget,
D.
High-level risks
Acceptance criteria.
Which document describes the necessary information to determine if a project is worth the
required investment?
A.
Cost baseline
B.
Service level agreement
C.
Memorandum of understanding
D.
Business case
Business case