Topic 2, Volume B
Which basic quality tool explains a change in the dependent variable in relationship to a change
observed in the corresponding independent variable?
A.
Cause-and-effect diagram
B.
Histogram
C.
Control chart
D.
Scatter diagram
Scatter diagram
Projects that share common outcomes, collective capability, knowledge, or skills are often grouped
into a:
A.
portfolio
B.
program
C.
selection
D.
sub portfolio
program
A project requires a component with well-understood specifications. Performance targets are
established at the outset, and the final contract price is determined after completion of all work
based on the seller's performance. The most appropriate agreement with the supplier is:
A.
Cost Plus Incentive Fee (CPIF).
B.
Fixed Price Incentive Fee (FPIF).
C.
Cost Plus Award Fee (CPAF).
D.
Fixed Price with Economic Price Adjustment (FP-EPA).
Fixed Price Incentive Fee (FPIF).
Which enterprise environmental factors may influence Plan Schedule Management?
A.
Cultural views regarding time schedules and professional and ethical behaviors
B.
Historical information and change control procedures
C.
Risk control procedures and the probability and impact matrix
D.
Resource availability and organizational culture and structure
Resource availability and organizational culture and structure
Which type of dependency used in the Sequence Activities process is sometimes referred to as
preferred logic, preferential logic, or soft logic?
A.
Internal
B.
External
C.
Discretionary
D.
Mandatory
Discretionary
Page 58 out of 157 Pages |
Previous |