In complex projects/ initiating processes should be completed:


A.

Within a work package.


B.

In each phase of the project.


C.

To estimate schedule constraints.


D.

To estimate resource allocations





B.
  

In each phase of the project.



A project manager requesting industry groups and consultants to recommend project intervention
is relying on:


A.

Communication models.


B.

Stakeholder participation.


C.

Expert judgment


D.

Enterprise environmental factors.





C.
  

Expert judgment



The degree, amount, or volume of risk that an organization or individual will withstand is called
risk:


A.

appetite


B.

tolerance


C.

threshold


D.

management





B.
  

tolerance



The following is a network diagram for a project


What is the critical path for the project?


A.

A-B-D-G


B.

A-B-E-G


C.

A-C-F-G


D.

A-C-E-G





C.
  

A-C-F-G



The following is a network diagram for a project

The total float for the project is how many days?


A.

3


B.

5


C.

7


D.

9





A.
  

3