Topic 2, Volume B
The following is a network diagram for a project.
The free float for Activity H is how many days?
A.
4
B.
5
C.
10
D.
11
4
Every project creates a unique product, service, or result that may be:
A.
tangible
B.
targeted
C.
organized
D.
variable
tangible
Correlated and contextualized information on how closely the scope is being maintained relative to
the scope baseline is contained within:
A.
project documents updates.
B.
project management plan updates.
C.
change requests.
D.
work performance information.
work performance information.
The most appropriate project life cycle model for an environment with a high level of change and
extensive stakeholder involvement in projects is:
A.
adaptive
B.
reflexive
C.
predictive
D.
iterative
adaptive
Whose approval may be required for change requests after change control board (CCB) approval?
A.
Functional managers
B.
Business partners
C.
Customers or sponsors
D.
Subject matter experts
Customers or sponsors