Topic 2, Volume B
In the Plan Procurement Management process, which source selection criteria analyzes if the
seller's proposed technical methodologies, techniques, solutions, and services meet the
procurement documents requirements?
A.
Technical approach
B.
Technical capability
C.
Business size and type
D.
Production capacity and interest
Technical approach
Stakeholder communication requirements should be included as a component of:
A.
enterprise environmental factors
B.
organizational process assets
C.
the project management plan
D.
the stakeholder register
the project management plan
Which element does a project charter contain?
A.
Management reserves
B.
Work breakdown structure
C.
Stakeholder list
D.
Stakeholder register
Stakeholder list
The following is a network diagram for a project
What is the critical path for the project?
A.
A-B-C-F-G-I
B.
A-B-C-F-H-I
C.
A-D-E-F-G-I
D.
A-D-E-F-H-I
A-B-C-F-G-I
The following is a network diagram for a project
How many possible paths are identified for this project?
A.
3
B.
4
C.
6
D.
7
4