Page 52 out of 157 Pages

Topic 2, Volume B

In the Plan Procurement Management process, which source selection criteria analyzes if the
seller's proposed technical methodologies, techniques, solutions, and services meet the
procurement documents requirements?


A.

Technical approach


B.

Technical capability


C.

Business size and type


D.

Production capacity and interest





A.
  

Technical approach



Stakeholder communication requirements should be included as a component of:


A.

enterprise environmental factors


B.

organizational process assets


C.

 the project management plan


D.

 the stakeholder register





C.
  

 the project management plan



Which element does a project charter contain?


A.

Management reserves


B.

Work breakdown structure


C.

Stakeholder list


D.

Stakeholder register





C.
  

Stakeholder list



The following is a network diagram for a project

What is the critical path for the project?


A.

A-B-C-F-G-I


B.

A-B-C-F-H-I


C.

A-D-E-F-G-I


D.

A-D-E-F-H-I





A.
  

A-B-C-F-G-I



The following is a network diagram for a project

How many possible paths are identified for this project?


A.

3


B.

4


C.

6


D.

7





B.
  

4