CAPM Practice Test


Page 51 out of 157 Pages

Topic 2, Volume B

The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:


A.

work package


B.

deliverable


C.

milestone


D.

activity





A.
  

work package



The scope management plan and scope baseline are contained in:


A.

organizational process assets


B.

a requirements traceability matrix


C.

the project charter


D.

the project management plan





D.
  

the project management plan



Which Manage Communications tool or technique focuses on identifying and managing barriers?


A.

Communication methods


B.

Information technology


C.

Communication models


D.

Information management systems





C.
  

Communication models



Which type of organizational structure is displayed in the diagram provided?



A.

Balanced matrix


B.

Projectized


C.

Strong matrix


D.

Functional





B.
  

Projectized



Outputs of the Control Communications process include


A.

expert judgment and change requests


B.

work performance information and change requests.


C.

organizational process asset updates and an issue log.


D.

project management plan updates and an issue log.





B.
  

work performance information and change requests.




Page 51 out of 157 Pages