Topic 1, Volume A
A project manager providing information to the right audience, in the right format, at the right time
is an example of which type of communication?
A.
Efficient
B.
Effective
C.
Push
D.
Pull
Effective
Scope, schedule, and cost parameters are integrated in the:
A.
Performance measurement baseline
B.
Analysis of project forecasts,
C.
Summary of changes approved in a period,
D.
Analysis of past performance.
Performance measurement baseline
A project in which the scope, time, and cost of delivery are determined as early as possible is
following a life cycle that is:
A.
Adaptive
B.
Predictive
C.
Incremental
D.
Iterative
Predictive
What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost
(AC) is $150, and the earned value (EV) is $50?
A.
0.50
B.
0.67
C.
1.50
D.
2.00
0.50
Which item is an input to the Define Activities process?
A.
Schedule data
B.
Activity list
C.
Risk register
D.
Scope baseline
Scope baseline
Page 5 out of 157 Pages |
Previous |