Topic 2, Volume B
Technical capability, past performance, and intellectual property rights are examples of:
A.
performance measurement criteria
B.
source selection criteria
C.
product acceptance criteria
D.
phase exit criteria
source selection criteria
The methodology that combines scope, schedule, and resource measurements to assess project
performance and progress is known as:
A.
Earned value management.
B.
Forecasting.
C.
Critical chain methodology.
D.
Critical path methodology
Earned value management.
Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk
Responses?
A.
Identify Risks
B.
Plan Risk Management
C.
Perform Qualitative Risk Analysis
D.
Perform Quantitative Risk Analysis
Perform Qualitative Risk Analysis
A special type of bar chart used in sensitivity analysis for comparing the relative importance of the
variables is called a:
A.
triangular distribution
B.
tornado diagram
C.
beta distribution
D.
fishbone diagram
tornado diagram
A full-time project manager with low to moderate authority and part-time administrative staff is
working in an organizational structure with which type of matrix?
A.
Strong
B.
Weak
C.
Managed
D.
Balanced
Balanced