Topic 2, Volume B
Project managers who lead by example and follow through on the commitments they make
demonstrate the key interpersonal skill of:
A.
influencing
B.
leadership
C.
motivation
D.
coaching
influencing
Which items are an output of the Perform Integrated Change Control process?
A.
Work performance reports
B.
Accepted deliverables
C.
Project management plan updates
D.
Organizational process assets
Project management plan updates
Which term describes an assessment of correctness?
A.
Accuracy
B.
Precision
C.
Grade
D.
Quality
Accuracy
The cost baseline and project funding requirements are outputs of which process in Project Cost
Management?
A.
Estimate Costs
B.
Control Costs
C.
Plan Cost Management
D.
Determine Budget
Determine Budget
The Project Human Resource Management process that involves confirming human resource
availability and obtaining the team necessary to complete project activities is:
A.
Acquire Project Team.
B.
Plan Human Resource Management.
C.
Manage Project Team.
D.
Develop Project Team.
Acquire Project Team.