Topic 2, Volume B
The following chart contains information about the tasks in a project
A.
2,000
B.
0
C.
1,000
D.
2,000
2,000
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedule performance index (5PI) for Task 4?
A.
0.83
B.
0.9
C.
1.11
D.
1.33
1.11
One of the key benefits of the Plan Human Resource Management process is that it:
A.
outlines team selection guidelines and team member responsibilities.
B.
establishes project roles and responsibilities.
C.
improves teamwork, interpersonal skills, and competencies.
D.
provides an accurate appraisal of team member performance.
establishes project roles and responsibilities.
Which Define Activities tool or technique is used for dividing and subdividing the project scope and
project deliverables into smaller, more manageable parts?
A.
Decomposition
B.
Inspection
C.
Project analysis
D.
Document analysis
Decomposition
Which type of analysis is used to determine the cause and degree of difference between the
baseline and actual performance?
A.
Schedule network analysis
B.
Reserve analysis
C.
Alternative analysis
D.
Variance analysis
Variance analysis
Page 45 out of 157 Pages |
Previous |