Topic 2, Volume B
A risk that arises as a direct result of implementing a risk response is called a:
A.
contingent risk
B.
residual risk
C.
potential risk
D.
secondary risk
secondary risk
The purpose of developing a project scope management plan is to:
A.
Manage the timely completion of the project.
B.
Ensure that the project includes all of the work required.
C.
Make sure the project will satisfy the needs for which it was begun.
D.
Reduce the risk of negative events in the project.
Ensure that the project includes all of the work required.
tool and technique used in the Develop Project Charter process is:
A.
change control tools
B.
expert judgment
C.
meetings
D.
analytical techniques
expert judgment
The following chart contains information about the tasks in a project.
Based on the chart, what is the cost performance index (CPI) for Task 2?
A.
0.8
B.
1
C.
1.25
D.
1.8
1.25
The following chart contains information about the tasks in a project
Based on the chart, what is the schedulevariance (SV) for Task 8?
A.
2,000
B.
1,000
C.
1,000
D.
2,000
1,000