Discount Offer
Go Back on CAPM Exam
Available in 1, 3, 6 and 12 Months Free Updates Plans
PDF: $15 $60

Test Engine: $20 $80

PDF + Engine: $25 $99



Pass exam with Dumps4free or we will provide you with three additional months of access for FREE.

CAPM Practice Test


Page 43 out of 157 Pages

Topic 2, Volume B

A disadvantage associated with virtual teams is that they:


A.

Require communication technology that is not readily available.


B.

Create difficulties when including people with disabilities.


C.

Often cannot accommodate teams that work different hours or shifts.


D.

Create the possibility for misunderstandings to arise





D.
  

Create the possibility for misunderstandings to arise



In which phase of team building activities do team members begin to work together and adjust
their work habits and behavior to support the team?


A.

Performing


B.

Storming


C.

Norming


D.

Forming





C.
  

Norming



Which project risk listed in the table below is most likely to occur?



A.

1


B.

2


C.

3


D.

4





B.
  

2



Which is an enterprise environmental factor?


A.

Marketplace conditions


B.

Policies and procedures


C.

Project files from previous projects


D.

 Lessons learned from previous projects





A.
  

Marketplace conditions



Project Stakeholder Management focuses on:


A.

project staff assignments


B.

project tea m acquisition


C.

managing conflicting interests


D.

communication methods





C.
  

managing conflicting interests




Page 43 out of 157 Pages
Previous