Topic 2, Volume B
A disadvantage associated with virtual teams is that they:
A.
Require communication technology that is not readily available.
B.
Create difficulties when including people with disabilities.
C.
Often cannot accommodate teams that work different hours or shifts.
D.
Create the possibility for misunderstandings to arise
Create the possibility for misunderstandings to arise
In which phase of team building activities do team members begin to work together and adjust
their work habits and behavior to support the team?
A.
Performing
B.
Storming
C.
Norming
D.
Forming
Norming
Which project risk listed in the table below is most likely to occur?
A.
1
B.
2
C.
3
D.
4
2
Which is an enterprise environmental factor?
A.
Marketplace conditions
B.
Policies and procedures
C.
Project files from previous projects
D.
Lessons learned from previous projects
Marketplace conditions
Project Stakeholder Management focuses on:
A.
project staff assignments
B.
project tea m acquisition
C.
managing conflicting interests
D.
communication methods
managing conflicting interests