Which Project Time Management process includes bottom-up estimating as a tool or technique?
A.
Estimate Activity Resources
B.
Sequence Activities
C.
Estimate Activity Durations
D.
Develop Schedule
Estimate Activity Resources
Progressively elaborating high-level information into detailed plans is performed by the:
A.
project management office
B.
portfolio manager
C.
program manager
D.
project manager
project manager
An input to the Control Quality process is:
A.
Activity attributes
B.
Quality control measurements
C.
Enterprise environmental factors
D.
Deliverables
Deliverables
The chart below is an example of a:
A.
Responsibility assignment matrix (RAM)
B.
Work breakdown structure (WBS)
C.
RACI chart
D.
Requirements traceability matrix
Requirements traceability matrix
Which Perform Quality Assurance tool or technique is used to identify a problem, discover the
underlying causes that lead to it, and develop preventative actions?
A.
Inspection
B.
Quality audits
C.
Design of experiments
D.
Root cause analysis
Root cause analysis