Which type of dependency is legally or contractually required or inherent in the nature of work and
often involves physical limitations?


A.

Mandatory


B.

Discretionary


C.

Internal


D.

External





A.
  

Mandatory



During which process does a project manager review all prior information to ensure that all project
work is completed and that the project has met its objectives?


A.

Monitor and Control Project Work


B.

Perform Quality Assurance


C.

Close Project or Phase


D.

Control Scope





C.
  

Close Project or Phase



An input to the Manage Project Team process is:


A.

Work performance reports.


B.

Change requests.


C.

Activity resource requirements.


D.

Enterprise environmental factors





A.
  

Work performance reports.



Which input provides suppliers with a clear set of goals, requirements, and outcomes?


A.

Procurement statement of work


B.

Purchase order


C.

Source selection criteria


D.

Bidder conference





A.
  

Procurement statement of work



A large portion of a projects budget is typically expended on the processes in which Process
Group?


A.

Executing


B.

Planning


C.

Monitoring and Controlling


D.

Closing





B.
  

Planning