Topic 2, Volume B
Which stakeholder approves a project's result?
A.
Customer
B.
Sponsor
C.
Seller
D.
Functional manager
Customer
Which process involves determining, documenting, and managing stakeholders' needs and
requirements to meet project objectives?
A.
Collect Requirements
B.
Plan Scope Management
C.
Define Scope
D.
Define Activities
Collect Requirements
Plan Communications Management develops an approach and plan for project communications
based on stakeholders' needs and requirements and:
A.
Available organizational assets
B.
Project staff assignments
C.
Interpersonal skills
D.
Enterprise environmental factors
Available organizational assets
Perform Integrated Change Control is the process of:
A.
Reviewing, approving, and managing all change requests
B.
Facilitating change management, manuals, or automation tools
C.
Comparing actual results with planned results in order to expand or change a project
D.
Documenting changes according to the change control system by the change control board
Reviewing, approving, and managing all change requests
When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is
an example of a:
A.
lead
B.
lag
C.
mandatory dependency
D.
internal dependency
lead