Topic 2, Volume B
In project management, a temporary project can be:
A.
Completed without planning
B.
A routine business process
C.
Long in duration
D.
Ongoing to produce goods
Long in duration
Which document in the project management plan can be updated in the Plan Procurement
Management process?
A.
Budget estimates
B.
Risk matrix
C.
Requirements documentation
D.
Procurement documents
Requirements documentation
Which type of probability distribution is used to represent uncertain events such as the outcome of
a test or a possible scenario in a decision tree?
A.
Uniform
B.
Continuous
C.
Discrete
D.
Linear
Discrete
Which change request is an intentional activity that realigns the performance of the project work
with the project management plan?
A.
Update
B.
Preventive action
C.
Defect repair
D.
Corrective action
Corrective action
Using parametric estimating, if an assigned resource is capable of producing 120 units per hour,
how many hours are required to produce 12,000 units?
A.
100
B.
120
C.
1,000
D.
1,200
100