Topic 2, Volume B
Which tool or technique used in the Control Procurements process can be conducted during the
execution of the project to verify compliance with deliverables?
A.
Procurement documents
B.
Inspection and audits
C.
Estimate budget
D.
Risk register
Inspection and audits
Job satisfaction, challenging work, and sufficient financial compensation are values related to
which interpersonal skill?
A.
Influencing
B.
Motivation
C.
Negotiation
D.
Trust building
Motivation
The following is a network diagram for a project.
The shortest non-critical path for the project is how many days in duration?
A.
10
B.
12
C.
14
D.
16
10
The following is a network diagram for a project
The critical path for the project is how many days in duration?
A.
10
B.
12
C.
14
D.
17
17
The component of the human resource management plan that includes ways in which team
members can obtain certifications that support their ability to benefit the project is known as:
A.
recognition and rewards
B.
compliance
C.
staff acquisition
D.
training needs
training needs