Topic 1, Volume A
Stakeholder satisfaction should be managed as a key project:
A.
Benefit
B.
Initiative
C.
Objective
D.
Process
Objective
Which cost is associated with nonconformance?
A.
Liabilities
B.
Inspections
C.
Training
D.
Equipment
Liabilities
Which tool or technique of the Define Activities process allows for work to exist at various levels of
detail depending on where it is in the project life cycle?
A.
Historical relationships
B.
Dependency determination
C.
Bottom-up estimating
D.
Rolling wave planning
Rolling wave planning
An output of the Create WBS process is:
A.
Scope baseline.
B.
Change requests.
C.
Accepted deliverables.
D.
Variance analysis.
Scope baseline.
A tool or technique used in the Control Procurements process is:
A.
Expert judgment.
B.
Performance reporting.
C.
Bidder conferences.
D.
Reserve analysis.
Performance reporting.