The iterative process of increasing the level of detail in a project management plan as greater
amounts of information become available is known as:
A.
Continuous improvement.
B.
Predictive planning.
C.
Progressive elaboration.
D.
Quality assurance.
Progressive elaboration.
An effective technique for resolving conflict that incorporates multiple viewpoints from differing
perspectives to achieve consensus and commitment is:
A.
smooth/accommodate.
B.
force/direct,
C.
collaborate/problem solve,
D.
compromise/reconcile.
collaborate/problem solve,
A temporary endeavor that creates a unique product or service is called a:
A.
Project
B.
Plan
C.
Program
D.
Portfolio
Project
Status of deliverables, implementation status for change requests, and forecasted estimates to
complete are examples of:
A.
Earned value management.
B.
Enterprise environmental factors.
C.
Organizational process assets.
D.
Work performance information
Work performance information
Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?
A.
Organizational process updates
B.
Quality metrics
C.
Change requests
D.
Quality control measurements
Quality metrics