Topic 1, Volume A
Which Collect Requirements output links the product requirements to the deliverables that satisfy
them?
A.
Requirements documentation
B.
Requirements traceability matrix
C.
Project management plan updates
D.
Project documents updates
Requirements traceability matrix
Units of measure, level of precision, level of accuracy, control thresholds, and rules of
performance measurement are examples of items that are established in the:
A.
Cost management plan.
B.
Work performance information.
C.
Quality management plan.
D.
Work breakdown structure.
Cost management plan.
Which type of dependency is established based on knowledge of best practices within a particular
application area or some unusual aspect of the project in which a specific sequence is desired,
even though there may be other acceptable sequences?
A.
External
B.
Internal
C.
Mandatory
D.
Discretionary
Discretionary
Sensitivity analysis is typically displayed as a/an:
A.
Decision tree diagram.
B.
Tornado diagram.
C.
Pareto diagram.
D.
Ishikawa diagram.
Tornado diagram.
The Monitoring and Controlling Process Group includes processes that:
A.
Establish the scope, objectives, and course of action of a project,
B.
Define a new project or a new phase of an existing project.
C.
Track, review, and regulate the progress and performance of a project.
D.
Complete the work defined in the project management plan.
Track, review, and regulate the progress and performance of a project.