The process of identifying and documenting relationships among the project activities is known as:


A.

Control Schedule.


B.

Sequence Activities.


C.

Define Activities.


D.

Develop Schedule.





B.
  

Sequence Activities.



Conditions that are not under the control of the project team that influence, direct, or constrain a
project are called:


A.

Enterprise environmental factors


B.

Work performance reports


C.

Organizational process assets


D.

Context diagrams





A.
  

Enterprise environmental factors



The organization's perceived balance between risk taking and risk avoidance is reflected in the
risk:


A.

Responses


B.

Appetite


C.

Tolerance


D.

Attitude





A.
  

Responses



An output of the Manage Stakeholder Engagement process is:


A.

change requests


B.

enterprise environmental factors


C.

the stakeholder management plan


D.

the change log





A.
  

change requests



Which process numerically analyzes the effect of identified risks on overall project objectives?


A.

Plan Risk Management


B.

Plan Risk Responses


C.

Perform Quantitative Risk Analysis


D.

Perform Qualitative Risk Analysis





C.
  

Perform Quantitative Risk Analysis