The process of identifying and documenting relationships among the project activities is known as:
A.
Control Schedule.
B.
Sequence Activities.
C.
Define Activities.
D.
Develop Schedule.
Sequence Activities.
Conditions that are not under the control of the project team that influence, direct, or constrain a
project are called:
A.
Enterprise environmental factors
B.
Work performance reports
C.
Organizational process assets
D.
Context diagrams
Enterprise environmental factors
The organization's perceived balance between risk taking and risk avoidance is reflected in the
risk:
A.
Responses
B.
Appetite
C.
Tolerance
D.
Attitude
Responses
An output of the Manage Stakeholder Engagement process is:
A.
change requests
B.
enterprise environmental factors
C.
the stakeholder management plan
D.
the change log
change requests
Which process numerically analyzes the effect of identified risks on overall project objectives?
A.
Plan Risk Management
B.
Plan Risk Responses
C.
Perform Quantitative Risk Analysis
D.
Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis