Topic 1, Volume A
Which tool or technique is used in the Develop Project Management Plan process?
A.
Pareto diagram
B.
Performance reporting
C.
SWOT analysis
D.
Expert judgment
Expert judgment
Lessons learned are created and project resources are released in which Process Group?
A.
Planning
B.
Executing
C.
Closing
D.
Initiating
Closing
When should quality planning be performed?
A.
While developing the project charter
B.
In parallel with the other planning processes
C.
As part of a detailed risk analysis
D.
As a separate step from the other planning processes
In parallel with the other planning processes
A key benefit of the Manage Communications process is that it enables:
A.
The best use of communication methods.
B.
An efficient and effective communication flow.
C.
Project costs to be reduced.
D.
The best use of communication technology.
An efficient and effective communication flow.
The ways in which the roles and responsibilities, reporting relationships, and staffing management
will be addressed and structured within a project is described in the:
A.
Human resource management plan.
B.
Activity resource requirements.
C.
Personnel assessment tools,
D.
Multi-criteria decision analysis.
Human resource management plan.