Topic 1, Volume A
Which tool or technique is used to manage change requests and the resulting decisions?
A.
Change control tools
B.
Expert judgment
C.
Delphi technique
D.
Change log
Change control tools
The planned work contained in the lowest level of work breakdown structure (WBS) components is
known as:
A.
Work packages.
B.
Accepted deliverables.
C.
The WBS dictionary.
D.
The scope baseline.
Work packages.
In which Knowledge Area is the project charter developed?
A.
Project Cost Management
B.
Project Scope Management
C.
Project Time Management
D.
Project Integration Management
Project Integration Management
The ability to influence cost is greatest during which stages of the project?
A.
Early
B.
Middle
C.
Late
D.
Completion
Early
Which process involves developing an approximation of the monetary resources needed to
complete project activities?
A.
Estimate Costs
B.
Control Costs
C.
Determine Budget
D.
Plan Cost Management
Estimate Costs
Page 17 out of 157 Pages |
Previous |