Inputs to the Plan Schedule Management process include:
A.
Organizational process assets and the project charter,
B.
Enterprise environmental factors and schedule tools.
C.
Time tables and Pareto diagrams.
D.
Activity attributes and resource calendars.
Organizational process assets and the project charter,
A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used
in which process?
A.
Identify Risks
B.
Control Risks
C.
Perform Quantitative Risk Analysis
D.
Perform Qualitative Risk Analysis
Identify Risks
Which Knowledge Area involves identifying the people, groups, or organizations that may be
impacted by or impact a project?
A.
Project Risk Management
B.
Project Human Resource Management
C.
Project Scope Management
D.
Project Stakeholder Management
Project Stakeholder Management
Which input to Collect Requirements is used to identify stakeholders who can provide information
on requirements?
A.
Stakeholder register
B.
Scope management plan
C.
Stakeholder management plan
D.
Project charter
Stakeholder register
Which process identifies whether the needs of a project can best be met by acquiring products,
services, or results outside of the organization?
A.
Plan Procurement Management
B.
Control Procurements
C.
Collect Requirements
D.
Plan Cost Management
Plan Procurement Management