CAPM Practice Test


Page 16 out of 157 Pages

Topic 1, Volume A

Inputs to the Plan Schedule Management process include:


A.

Organizational process assets and the project charter,


B.

Enterprise environmental factors and schedule tools.


C.

Time tables and Pareto diagrams.


D.

Activity attributes and resource calendars.





A.
  

Organizational process assets and the project charter,



A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used
in which process?


A.

 Identify Risks


B.

Control Risks


C.

Perform Quantitative Risk Analysis


D.

Perform Qualitative Risk Analysis





A.
  

 Identify Risks



Which Knowledge Area involves identifying the people, groups, or organizations that may be
impacted by or impact a project?


A.

Project Risk Management


B.

Project Human Resource Management


C.

Project Scope Management


D.

Project Stakeholder Management





D.
  

Project Stakeholder Management



Which input to Collect Requirements is used to identify stakeholders who can provide information
on requirements?


A.

Stakeholder register


B.

Scope management plan


C.

Stakeholder management plan


D.

Project charter





A.
  

Stakeholder register



Which process identifies whether the needs of a project can best be met by acquiring products,
services, or results outside of the organization?


A.

Plan Procurement Management


B.

Control Procurements


C.

Collect Requirements


D.

Plan Cost Management





A.
  

Plan Procurement Management




Page 16 out of 157 Pages