Topic 1, Volume A
Which process determines the risks that may affect the project and documents their
characteristics?
A.
Control Risks
B.
Plan Risk Management
C.
Plan Risk Responses
D.
Identify Risks
Identify Risks
An example of a group decision-ma king technique is:
A.
Nominal group technique.
B.
Majority.
C.
Affinity diagram.
D.
Multi-criteria decision analysis.
Majority.
A risk response strategy in which the project team shifts the impact of a threat, together with
ownership of the response, to a third party is called:
A.
mitigate
B.
accept
C.
transfer
D.
avoid
transfer
An output of the Plan Quality Management process is:
A.
A process improvement plan,
B.
Quality control measurements.
C.
Work performance information,
D.
The project management plan
A process improvement plan,
A project manager should document the escalation path for unresolved project risks in the:
A.
Change control plan
B.
Stakeholder register
C.
Risk log
D.
Communications management plan
Communications management plan