Which input to the Manage Stakeholder Engagement process provides guidance on how
stakeholders can best be involved in a project?


A.

Feedback analysis


B.

Stakeholder analysis


C.

Communication management plan


D.

Stakeholder management plan





D.
  

Stakeholder management plan



A method of obtaining early feedback on requirements by providing a working model of the
expected product before actually building is known as:


A.

Benchmarking.


B.

Context diagrams.


C.

Brainstorming.


D.

Prototyping.





D.
  

Prototyping.



Which stakeholder classification model groups stakeholders based on their level of authority and
their active involvement in the project?


A.

Power/influence grid


B.

Power/interest grid


C.

Influence/impact grid


D.

Salience model





A.
  

Power/influence grid



Which Plan Schedule Management tool or technique may involve choosing strategic options to
estimate and schedule the project?


A.

Facilitation techniques


B.

Expert judgment


C.

Analytical techniques


D.

Variance analysis





C.
  

Analytical techniques



The process of estimating the type and quantity of material, human resources, equipment, or
supplies required to perform each activity is known as:


A.

Collect Requirements.


B.

Conduct Procurements.


C.

 Estimate Activity Durations.


D.

Estimate Activity Resources





D.
  

Estimate Activity Resources