Go Back on CAPM Exam
Available in 1, 3, 6 and 12 Months Free Updates Plans
PDF: $15 $60

Test Engine: $20 $80

PDF + Engine: $25 $99

CAPM Practice Test


Page 10 out of 157 Pages

Topic 1, Volume A

Market conditions and published commercial information are examples of which input to the
Estimate Costs process?


A.

Scope baseline


B.

Organizational process assets


C.

Enterprise environmental factors


D.

Risk register





C.
  

Enterprise environmental factors



An output of the Develop Project Team process is:


A.

Organizational process assets.


B.

Enterprise environmental factors updates.


C.

Project staff assignments.


D.

Organizational charts and position descriptions.





B.
  

Enterprise environmental factors updates.



The process of confirming human resource availability and obtaining the team necessary to
complete project activities is known as:


A.

Plan Human Resource Management.


B.

Acquire Project Team.


C.

Manage Project Team.


D.

Develop Project Team.





B.
  

Acquire Project Team.



Which item is an example of personnel assessment?


A.

Resource calendar


B.

Tight matrix


C.

Team-building activity


D.

Focus group





D.
  

Focus group



The Plan Stakeholder Management process belongs to which Process Group?


A.

Executing


B.

Initiating


C.

Planning


D.

Monitoring and Controlling





C.
  

Planning




Page 10 out of 157 Pages
Previous