A reward can only be effective if it is:


A.

Given immediately after the project is completed.


B.

Something that is tangible.


C.

Formally given during project performance appraisals.


D.

Satisfying a need valued by the individual





D.
  

Satisfying a need valued by the individual



Project deliverables that have been completed and checked for correctness through the Control
Quality process are known as:


A.

Verified deliverables.


B.

Validated deliverables.


C.

Acceptance criteria.


D.

Activity resource requirements.





A.
  

Verified deliverables.



An output of the Perform Integrated Change Control process is:


A.

Deliverables.


B.

Validated changes.


C.

The change log.


D.

The requirements traceability matrix.





C.
  

The change log.



During which process does the project team receive bids and proposals?


A.

Conduct Procurements


B.

Plan Procurements


C.

Estimate Costs


D.

Control Budget





A.
  

Conduct Procurements



The process of monitoring the status of the project and product scope as well as managing the
changes to the scope baseline is known as:


A.

Validate Scope.


B.

Plan Scope Management.


C.

Control Scope.


D.

Define Scope.





C.
  

Control Scope.