Topic 1, Volume A
What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual
cost (AC) is $50, and the earned value (EV) is $25?
A.
$50
B.
$100
C.
$125
D.
$175
$125
The business needs, assumptions, and constraints and the understanding of the customers needs
and high-level requirements are documented in the:
A.
Project management plan.
B.
Project charter.
.
C.
Work breakdown structure.
D.
Stakeholder register
Project charter.
.
Which Process Group and Knowledge Area include the Sequence Activities process?
A.
Executing Process Group and Project Time Management
B.
Executing Process Group and Project Cost Management
C.
Planning Process Group and Project Time Management
D.
Planning Process Group and Project Cost Management
Planning Process Group and Project Time Management
In the Plan Stakeholder Management process, expert judgment is used to:
A.
Provide information needed to plan appropriate ways to engage project stakeholders.
B.
Ensure comprehensive identification and listing of new stakeholders.
C.
Analyze the information needed to develop the project scope statement.
D.
Decide the level of engagement of the stakeholders at each required stage.
Decide the level of engagement of the stakeholders at each required stage.
The degree, amount, or volume of risk that an organization or individual will withstand is known as
its risk:
A.
Analysis
B.
Appetite
C.
Tolerance
D.
Response